Kitchen Remodel Estimator

Built the way a Columbus contractor actually bids it — measure the box, schedule the trades, price the work. Watch your estimate get built, step by step.

This kitchen remodel cost calculator is not a lookup table. It runs the same engine a Columbus contractor bids with: man-hours at $85 an hour, management days, plumbing and electrical subs, install material, cabinets and counter, a 20% construction contingency, then appliances and structural work on top. Every figure on this page comes out of that engine.

1. Your Kitchen Layout

Estimating starts with the box. Kitchens vary widely — pick the shape closest to yours. You don't measure anything; we work from the typical quantities each layout implies.

Adding a center island? That's a checkbox on the conditions step — it layers onto any of these.

2. How Big, Really?

Kitchens are designed tight around the work triangle, so a bigger kitchen is mostly more material, modestly — not a wild jump.

3. Appliance Grade

This is the single biggest swing — a basic package vs. a pro range can differ by an order of magnitude. Shown as its own line at typical all-in cost; who buys it doesn't change the project cost.

4. What Your House May Force

These ride on top of the base — your home's age and structure decide them, not your taste. Each is a flagged assumption with a change-order trigger.

Your home's age predicts hidden cost — older homes often force rough plumbing and wiring replacement.

Only stone and laminate are estimated here. Quartz, solid-surface, butcher block, tile and true bespoke tops vary too much to price blind — email us for a custom estimate.

Estimated project cost
—

How this gets built — your schedule

Price is a real schedule, not a magic number. Each phase is real man-hours, rounded to working days.

Working days are gauged from total man-hours at a standard two-person crew (≈16 man-hours/day). Real duration shifts with crew size and trade sequencing — parallelizable work (e.g. demo) compresses with added help, while cure- and inspection-bound work (e.g. tile, drywall) does not. Treat the day count as a planning estimate, not a fixed schedule.

Where the money goes

What we assumed

    Not included

      This is an educated estimate from real Columbus contractor pricing — not a national average. Site conditions found on demo are surfaced as change orders before any work proceeds.

      Want this as a printable estimate?

      The estimator already gave you the number — no email required to use it. If you'd like the full itemized breakdown, the day-by-day schedule, and the assumptions written up as a printable estimate, leave your email and we'll send it as a follow-up.

      No spam, ever. We send your estimate and follow up once.

      How this calculator builds the number

      Every combination runs through the same seven steps, in this order. Nothing is looked up from a national average, and nothing is rounded until the end.

      1. Labor. Total in-house man-hours for the gut — demo through finish paint — multiplied by the crew rate, currently $85 an hour. A standard 10×10 gut is 148 man-hours; a large 12×14 is 192. One working day is a two-person crew at 16 man-hours, so 148 man-hours rounds to ten working days.
      2. Management. Management and inspection days multiplied by two billed hours a day at the on-site coordination rate, currently $155 an hour. A standard job carries ten of those days, which is $3,100.
      3. The cost lines that ride inside the contingency. The plumbing sub ($500 with the sink staying put, $1,500 once rough plumbing is included); the electrical sub ($1,500 on reusable circuits, $3,500 to isolate the kitchen, $6,000 when the panel is replaced too); a fixed $2,750 install-material lump covering demo, dumpster, framing, drywall and drywall finish, paint, finish carpentry and miscellany; cabinets at $3,250; and the countertop — stone at fabricator cost times a 1.30 sub markup, laminate at material cost with no markup.
      4. The contingency. Labor, management and every line in step 3 are summed into one bucket and multiplied by 1.20. On a standard 10×10 that bucket is $26,630 and the contingency line is $5,326.
      5. Standalone lines on top. The appliance grade and any structural overlay — a load-bearing wall with a steel beam, engineered structural plans — are added after the contingency, each at its own markup. They are never inside it, which is why a Luxury appliance package adds exactly $76,044 to a standard 10×10 no matter what else is selected.
      6. The small-project service fee. $125, and only when total in-house man-hours fall below eight. A kitchen gut never triggers it — the engine's own floor is 148 man-hours.
      7. The subtotal, and the cabinet-grade range under it. The headline "Estimated project cost" is the subtotal at the $3,250 representative cabinet cost. The line beneath it re-runs all six steps above at the $2,500 and $4,000 ends of the cabinet band and changes nothing else, which is why it always lands $900 either side of the headline.

      The countertop line is the one most people want to see on its own. It is $1,950 for a single stone slab on a standard kitchen, $4,550 once a center island is added, and $7,800 on a large kitchen with an island. Laminate is $400 for stock preformed ten-foot sections and $900 custom-made.

      Three sample outputs

      Three real runs of the tool. Nothing changed between them except the options listed in the first column.

      Sample outputs from this calculator, 2026 Columbus rates.
      What was selectedEstimated project costCabinet-grade range
      Galley, 10×10, no appliance line, stock laminate counter, sink staying put$28,356$27,456 – $29,256
      Basic L, 10×10, Mid appliances, stone counter, rough plumbing included$39,044$38,144 – $39,944
      U-shape, 10×10, High appliances, stone counter plus a center island, isolated circuits$57,514$56,614 – $58,414

      The first two are the same size kitchen. The $10,688 between them is a laminate top swapped for stone, rough plumbing switched on, and a mid-grade appliance package added — three answers, not three hundred. The third adds an island and new circuits on top of that: its construction cost before appliances is $37,476, and the High appliance line riding on top is $20,038.

      What the estimate includes, and what it leaves out

      Included on every run, whatever is selected: full in-house gut labor from demo through finish paint; standard dust protection, which is a drop cloth on the construction path and a zippered door at the work area, added at no cost; management and inspection coordination at the on-site rate; cabinets and countertop as their own line items; and appliances at typical all-in cost when a grade is chosen — who actually buys them does not change the project cost.

      • Permits and inspection fees are not in the number. They are paid to the municipality, and whether a kitchen needs one depends on what moves — when a Columbus kitchen needs a permit covers the triggers.
      • HVAC duct relocation, a main-stack rebuild and a panel replacement are excluded unless the matching condition is checked on step 4.
      • Unforeseen conditions found on demo are not priced in advance. They are surfaced as change orders before work proceeds rather than absorbed quietly.
      • Only stone slab and laminate counters are estimated. Quartz, solid surface, butcher block, tile and bespoke tops vary too much to price blind.
      • Some kitchens get no figure at all. A kitchenette or very small single-wall kitchen, a partial or cosmetic remodel, a custom or non-standard layout, and structural work beyond the listed conditions are all routed to a custom estimate instead.

      What is variable inside the number

      • The cabinet-grade range is the only spread the tool prints, and it is always $900 either side. A cabinet line beyond the $2,500–$4,000 band is something a real quote has to settle.
      • Every condition is additive. An island, isolated circuits and rough plumbing are measured against the reusable-circuits, rough-required baseline — they add, they never subtract from a total shown elsewhere.
      • The year the home was built is context, not its own dollar line. It drives the assumption flags — galvanized drains, knob-and-tube, lath and plaster, mortar-bed subfloor — and the rough-plumbing default.
      • Working days are a planning estimate. They are gauged from total man-hours at a two-person crew. Parallelizable work such as demo compresses with extra help; cure- and inspection-bound work such as tile and drywall does not.

      When to get a real quote instead

      The tool says so itself on the way in: it cannot price a kitchenette, a partial or cosmetic remodel, a custom layout, or structural work beyond the conditions on step 4. Those need a person, not a calculator.

      Even well inside its range, treat what comes out as a planning range rather than a bid. A real quote needs a site visit — what is behind the plaster, where the stack actually runs, whether the panel has room for the circuits a current-code kitchen needs. It is worth getting one when the house predates 1980, when the layout is moving, or when two scopes with real money between them are still on the table.

      What to do next

      If the number here is close to what you expected, the guide to kitchen remodel cost in Columbus has the full layout and size tables, six worked examples and the working-day counts behind them. If the permit question is the open one, kitchen permits in Columbus covers what Building & Zoning Services triggers on. If the island toggle on step 4 is the decision you are stuck on, island sizing has the clearances that decide whether one fits. And to see a single budget followed end to end, what a $35K Columbus kitchen remodel gets you walks one through line by line.